2020-05-12 13:40 | Report Abuse

First of all i did not mean you say Ageson cannot deliver!

shortinvestor77 If it can deliver the sand, everything will be smooth, PO will continue. If cannot deliver, just the PO will be cancelled by the Purchaser.
12/05/2020 1:16 PM

shortinvestor77 Deal is there, just how to deliver only. can or cannot?
12/05/2020 1:17 PM

Stock

2020-05-12 13:29 | Report Abuse

YES EXACTLY! SO THOSE FUZZ AND BUZZ NEWS ARE NOW HAVE BEEN CLEARED!

Stock

2020-05-12 13:24 | Report Abuse

shortinvestor77 and Goodprofit(calvintaneng), I just dig in for more good news from Ageson, those sand are mine and use huge ship carrier send it to China, and they just need to place those sand into the designated place where china wanted, no need to deliver those sand to sand trucks! So guys, Give me a good reason WHY Ageson can't delivered?

Stock

2020-05-12 13:04 | Report Abuse

CITADEL , show me the fake MOU, I will go report to bursa!

Stock
Stock

2020-05-12 09:54 | Report Abuse

Now can you dig it...........
S>U>C>K>E>R>S!

paulthesotong Why mention name,
? Viva, u really a big axe.
12/05/2020 9:52 AM

Stock

2020-05-12 09:38 | Report Abuse

HI freetospeak----- calvin the b.a.s.t.x.r.d dog use fake account to blast here, name as air01557, DAMAL666, paulthesotong, goodtrade, Value888.........

Stock

2020-05-12 09:37 | Report Abuse

NO AP? JV with Sultan for? haha another sour grape! No AP you dare and go dig and sell sand argh? NO AP you dare to announce to the whole world you have BIG SAND PROJECT argh? hahaha

Stock

2020-05-12 09:32 | Report Abuse

Mark my words, Ageson this week sure break rm0.20!

Stock

2020-05-12 09:28 | Report Abuse

Throwback........

Stock: [AGES]: AGESON BERHAD

May 10, 2020 10:25 PM | Report Abuse

Good evening Happy investors of Ageson, Just my 2cent and correct me if i am wrong, About those fuzz and buzz news, Is a govt servant representing the entire federal and state govt? Is it all business collaboration needs to report to govt servant? Wah like that very tired lo, total all 32 ministers and 37 deputy ministers.....impressive! Apparently, this is just a business collaboration..... Does anyone here knows that most AP are owned by who? Loads of Rumors says AP mostly owned by ROYAL FAMILIES, rumors only ok...... Luckily i bought Ageson at price range 0.075, still got lots of stock.....Who wants, can buy from me!

Stock

2020-05-10 22:50 | Report Abuse

NancyDrewWhite, confirm jio you for huat cai! Let's all together huat cai from Ageson!

Stock

2020-05-10 22:25 | Report Abuse

Good evening Happy investors of Ageson, Just my 2cent and correct me if i am wrong, About those fuzz and buzz news, Is a govt servant representing the entire federal and state govt? Is it all business collaboration needs to report to govt servant? Wah like that very tired lo, total all 32 ministers and 37 deputy ministers.....impressive! Apparently, this is just a business collaboration..... Does anyone here knows that most AP are owned by who? Loads of Rumors says AP mostly owned by ROYAL FAMILIES, rumors only ok...... Luckily i bought Ageson at price range 0.075, still got lots of stock.....Who wants, can buy from me!

Stock

2020-05-08 15:04 | Report Abuse

for tower crane inside the building, there is not way to lower down. so usually the tower crane will hoist up a smaller crane and build it on top of building. that this second crane will proceed to dismantle tower crane and hoist it down. then to remove second crane, a even smaller crane would be hoisted up. same as the first crane, the third crane will dismantle the second crane and hoist it down. the third crane is generally smaller enough that can dismantle by pieces and carry through staircase / lift. below is picture of tower crane inside building boundary

Stock

2020-05-08 15:04 | Report Abuse

there are few method to bring down the crane. if the tower crane is not fix inside the boundary of building but outside attached to building, then the tower crane can dismantle itself. by taking out the mast 1 by 1 which subsequently lower down itself. until a certain low level, then will use the mobile crane to dismantle. below is the picture of tower crane that fix outside boundary of building.

Stock

2020-05-08 15:01 | Report Abuse

for tower crane, they use mobile crane to fix tower crane at bottom. then the tower crane will keep add the mast on itself to increase its height. can found those video on youtube in fact.

for backhoe, normal construction work don't need it at top level. but of course got exception got certain case. demolition of building usually need backhoe on the of building if it were to demolish 1 by 1. and yes, they use mobile crane to lift up the backhoe to the building. u will surprise that there were actually 500tonne mobile crane available for rent. daily rental could be abt RM50k a day.

Stock

2020-05-08 14:59 | Report Abuse

I'm not specialized in piling work too hence limited knowledge in piling......

Stock

2020-05-08 14:57 | Report Abuse

the cost is calculated by sellable area. so ur 30 storey condo, how many area is sellable? high end 1?

Stock

2020-05-08 14:54 | Report Abuse

Printing U.S Dollar Dollar Dollar ,
fyi
Appearance from highest to lowest
Marble
Granite
Quartz
Solid surface
Laminate plywood
Tile

Quality from highest to lowest
Granite
Quartz
Solid surface
Marble
Tile
Laminate plywood

very common using dark galaxy as it is granite plus it got a lot of shinny gold spot inside so make it look beautiful

Stock

2020-05-08 14:52 | Report Abuse

200kg seems more than enough for beam. well, u can do sampling measurement. take a beam at ground floor and measure a beam. best is u have the accurate qty, because u have more qty, ur price no longer competitive, ur price less qty, u get the job and suffer loss.

so I understand ur position, possible request to get the rebar qty in contract is "provisional"?

Stock

2020-05-08 14:46 | Report Abuse

poundage is for temporary estimation / general checking only. engineer got their own structural design when come to this. (eg. the area of the steel and area of beam when come to section got certain ratio to comply therefore poundage is relate but is not 100% accurate) and also depend on the loading the poundage figure might deviated a lot.

Stock

2020-05-08 14:25 | Report Abuse

HI babiking, used to be vincci from french. nowadays china taken 4 out of top 5 list i think

Stock

2020-05-08 14:23 | Report Abuse

should have la. I also interested to know. without engineer endorsement, I doubt it is fit to live in.

Stock

2020-05-08 14:21 | Report Abuse

Umbrella Corp , actually in langkawi also have a lot of this. they build a lot of cabin made it become a hotel next to the beach and run commercially.

Stock

2020-05-08 14:19 | Report Abuse

Umbrella Corp , a habitable building is required to be conform the requirement as stated in by law.

this is the one I'm frequently refer for. undang-undang kecil bangunan, wilayah persekutuan kl 1985...

Stock

2020-05-08 14:12 | Report Abuse

bro, feel free to give opinion. I'm also not really know everything. just sharing what I know here only

Stock

2020-05-08 14:10 | Report Abuse

1. Steel is much more expensive than concrete per tonne, but if steel is used to reinforce concrete it is usually less than 1 percent by cross sectional area compared with the concrete. Even in concrete columns the steel is usually less than 4 percent. For steel construction using I beams and steel universal columns, the steel is a stronger material than concrete alone when of equal cross section, with good strength in both tension and compression, compared to the concrete which has only a fairly good strength in compression, with its limited strength in tension usually ignored for design purposes in reinforced concrete..
2. prices for normal glass windows is around ~RM12 psft over here. including aluminium frame and installation. if i'm not mistaken.
3. cost for dual glazed, and tempered glass also depend on the frame quality. IINM it should be around RM50-70 psft depending on the thickness & type.
4. flat roofs constructed by concrete slabs will need asphalt treatment. not usually recommended for residential as it requires much more maintenance.
5. jkr spec need 1 year is the soil is new, not compacted. existing land after clearing usually don't need as long.
6. depending on area. and who you ask.
7. yeah. don't pick problematic ones. also higher priced doesn't mean better quality.

Stock

2020-05-08 14:04 | Report Abuse

YoungTycoonWILL

fyi

1. depends. concrete beam is cheaper, but in some situation it's just not feasible to erect a concrete beam and a steel beam is a better option.
2. water table. and maybe soil condition. if both is preferable, then it makes much sense to build underground.
3. we're heavily designing (and implementing) passive cooling in our build. windcatcher, wind stack effect, directed airflow, insulated roof, natural ventilation. even considering AAC bricks. maybe you could take some pointers from our build.

Stock

2020-05-06 15:04 | Report Abuse

Yes agree with teareader818 , already told its from philipines to hong kong,------ GoodTrade @ViVa ... It's understandable if u r talking about 100 ton mining lorry in Malaysia ... 400 or 500 ton lorry had to find here ... (((((by the way, pls show me your 350,000 ton transporter n which road can accommodate such huge n heavy load without damaging or sinking the road ...))))))-------

fyi

its from philipines to china, its a sea-route, how to show?

By the way, if its using land roads, it is at overseas....... even if i ask you malaysia road.
sample: perlis, university utara malaysia have a project, how ,where and which road can accommodate such huge n heavy load without damaging or sinking the road, can you show me? GoodTrade

Stock

2020-05-06 14:53 | Report Abuse

GoodTrade - land transportation problem, need to go to the site, and find out the answer. lolz

Stock

2020-05-06 14:27 | Report Abuse

GoodTrade, 350,000 ton transporter is a ship, not a road transport..... and i think its from Philippines to china right, so which road can accommodate such huge n heavy load without damaging or sinking the road ...? Even if i ask you about Perlis road i dun think you can either answer me that! right?

Stock

2020-05-06 13:28 | Report Abuse

Goodtrade, i forgot. Overseas big sand trucks can carry 450-500 tonnes per trip........So this is do-able especially in China!

Stock

2020-05-06 13:24 | Report Abuse

Hi there KennyDowJones, for timber door, high density of solid hardwood is the material made up a fire rated door. therefore it would be very heavy. fire rated door that mandated in the building listed in the bylaw required bomba certification. so those door supplier with bomba cert is suffice. gayamurni is quite a reputable 1 but also pricey la.

partition wise, i'm very confident with boral brand of gypsum board. for sound proofing, can sandwiched rockwool between the gypsum board at the ratio of 60kg/m3 for heavy sound insulation.

Stock

2020-05-06 13:12 | Report Abuse

GoodTrade ......large sand carrier can carry up to about 350000 tonnes per trip. So it means only 2 large sand carrier can kaotim 600000 tonnes of sands per day.......

Stock

2020-05-06 12:35 | Report Abuse

GoodTrade,you are into sands and stones? How do you calculate this?

GoodTrade @ov123 ... This biz deal will involve a massive logistic n transportation ... Imagine how to transport 4,500 x 50,000 tonnes of sand to sea port in a year, it is about 600,000 tonnes a day (12 x 50,000 tonnes) ... May require 60,000 trips to the sea port everyday by using a 10 tonnes lorry ... How many 10 tonnes lorry are needed ? ... This is just my simple calculation ...

Where do you get these numbers? Mind to answer? Your from logistic n transportation? or which type of Construction aggregate your in?

Stock

2020-05-06 12:29 | Report Abuse

Yes, besides construction.....also do sands......and many types of stones are available such as basalt, marble, limestone, sandstone, quartzite, travertine, slate, gneiss, laterite, and granite which can be used as construction materials.

Stock

2020-05-06 12:19 | Report Abuse

I do have degree, my family owns a construction company........pass down from my grandfather.

Stock

2020-05-06 12:14 | Report Abuse

DatoSeriJohnnyWalker, steel structure at abt RM7/kg, while in reinforced concrete, the rebar is abt RM3.5/kg plus u actually use lesser weight of rebar as it is a combination of rebar and concrete.

general estimation (not 100% accurate but is abt there, market price in big volume)

brickwall RM45/m2
glass is RM450/m2 (RM250 aluminium and frame + RM200 tempered glazing) low-e double glazing type will cost double on the glazing itself.

straight away u can build sub-structure. the set of foundation structure is the thing matter than u wait the land set.

cost budgeting, u need to have budget first. define the area u wanna build i.e. 2000sqft then allow a budget by 2000sqft x RM150. (the cost is vary depend on the quality u want. from this budget only start to work on the rest. this can be done through feasibility study, i did elaborate a little bit in previous post.

contractor, get those design and build 1 stop do everything including they hire architect and runner for approval relevant to local authority.

Stock

2020-05-06 11:40 | Report Abuse

BABIKING,what ur employer mean? employer mean developer in construction industry context.

base on percentage of total building cost for professional like Architect, Engineer, QS. those are known as professional fee.

for contractor is base on value of works.

Stock

2020-05-06 11:22 | Report Abuse

BABIKING .....if ur brickwall haven't lay, then the cost can be reduce by add a layer of "poly" form, around 50mm thick b4 do plastering work. therefore u don't need gypsum board. generally the cost increase also just not that much. but on completed building, overall it would be more costly

Stock

2020-05-06 11:21 | Report Abuse

Actually guys............concrete cheap, steel expensive.

basically in construction there are 2 type of cost involve. cost for temporary work and cost for permanent work. permanent work is like brickwall, concrete slab and etc. once the permanent work done, it remain there and will not be remove. temporary work is those cost spent on the work and will not be part of the building. example such as rental of machinery, scaffolding for support and etc. for basement the cost for temporary work will increase. so u pay for more to build a basement than to add 1 level on top.

the basement work is generally fine to do at Malaysia la. depend on location, the basement work difficulty is different also. like in golden triangle, the ground water level is high, so ur basement work is even tougher.

those "red brick" u see is better than cement-sand brick. cement-sand brick easily let water seep through. hence not advisable to do on external wall. but it could be done also.

glass wall is more on aesthetic. definitely glass wall is expensive, around 15 times expensive than brickwall

Stock

2020-05-06 11:10 | Report Abuse

Printing U.S Dollar Dollar Dollar ,chemical bolt have way better strength than the threaded plug u mention. depend on size each chemical bolt will cost u abt RM50 especially hilti / ramset brand

Stock

2020-05-06 11:06 | Report Abuse

Printing U.S Dollar Dollar Dollar, Hello! no standard. for rapid construction, usually will use steel column (could be in circular hollow section or square hollow section) as straight away can deliver to site and fix it on the spot. to fix it on the concrete slab, first have to drill in chemical bolt for better anchor to the base of column.

Stock

2020-05-06 10:42 | Report Abuse

YoungTycoonWILL , i forget about the scale. I'm quite sure the number mention is in mm. meaning 3.75m for B1, 6m for L and 4m for 1st floor.

I don't know why u need to divide by 50 if the 3750 is in feet. coz if that is really 3750ft then convert to m is 3750 / 3.281 = 1142.94m that B1 alone is the tallest building in the world!!


added: ohh, the divide 50 is scale. u do't have to divide, forget about the scale if u can get the dimension from drawing. the scale meant for u to check if u can't see the dimension in the drawing

Stock

2020-05-06 10:42 | Report Abuse

3750, 6000 and 4000 are in mm la...so it's really 3.75m, 6m and 4m.........

Stock

2020-05-06 10:39 | Report Abuse

BECAUSE THIS IS A CONSTRUCTION COMPANY......

Stock

2020-05-06 10:39 | Report Abuse

Anything about CONSTRUCTION, yes of course!

Stock

2020-05-06 10:36 | Report Abuse

morning guys.....

Stock

2020-05-05 13:50 | Report Abuse

BABIKING, yes, its mean u spend more overall. or maybe u need save 10 years electric bill get back those cost? plus when u put rockwool and gypsum board, ur wall set back a little bit. make ur room smaller.

brickwall generally not good in thermal insulation

to save that better get inverter aircond

oh ya, overall u still can be green (save energy and sources of thing)
1. fix rainwater harvesting tank to collect rainwater for flushing toilet
2. fixing solar panel (but not really cost effective at the moment as it is so expensive)
3. put more glazing panel at windows so fully utilize daylight
4. LED light fitting for lesser energy consumption


Sime Darby is going toward this direction when developing properties many years ago........

Stock

2020-05-05 13:47 | Report Abuse

BABIKING, apply tinting on your windows. beside that there other way is to get a contractor that do a layer of gymsum board on the wall, apply a layer of rockwool on the wall surface b4 use the gypsum board to close up. but not cost efficient i think

Stock

2020-05-05 13:45 | Report Abuse

Ezy,BABIKING......because hammerhead span too long. especially at klang valley, the site is small hence hammerhead tower crane span beyond the boundary of site which is prohibited by local authority.