@Tong Coleman this counter won't move until the debt against Maybank is settled, which need to wait till April to see if can success negotiate with them.
SCOMI GROUP BHD - MONTHLY ANNOUNCEMENT ON THE STATUS OF DEFAULT IN PAYMENT TO AXIS BANK LIMITED PURSUANT TO PARAGRAPH 9.19A OF THE BURSA MALAYSIA SECURITIES BERHAD This announcement is dated 18 March 2019.
Kindly be advised that at the request of SCOMI, trading in the Company's securities has been suspended with effect from 10.57 a.m., Thursday, 4 April 2019 pending a material announcement.
It all depends on how the debt restructing and updating report goes by next Monday and the loads of outstandning problem with monorail in Mumbai, India and Sao Paulo, Brazil. Not out ofthe woods yet. Nonetheless , a positive start and some breathing space if and only if the contract win with RapidKL is substantial.
Wew...IJM Corporation got 200mil shares or 20+% in scomi...pn17 then jialat already...scomi can sustain earning or not?bank default already...can get any finance from other bank or not to finance contract award...no bank finance then right issue ah?hehe
Agreement reached: Under the settlement agreement, Prasarana will make payments amounting to RM181mil to STP for refurbishment works to repair five sets of four-car monorail trains that have stopped working since January 2018
PETALING JAYA: A settlement has finally been reached between Scomi Group Bhd ’s subsidiary, Scomi Transit Projects Sdn Bhd (STP), and Prasarana Malaysia Bhd with the signing of a new contract for RM303mil, ending their dispute relating to the Kuala Lumpur Monorail Fleet Expansion Project Contract back in June 3, 2011.
This project was for the completion of the upgrade of the Kuala Lumpur monorail stations and the electrical and mechanical system, the construction of a new depot, and delivery of 12 sets of new four-car trains.
“STP and Prasarana are entering into the settlement agreement for the purpose of amicably determining the legal proceedings between the parties, while concurrently moving forward with the completion of the project,” said Scomi Group in a filing with Bursa Malaysia.
Under the settlement agreement, Scomi Group said Prasarana would make payments amounting to RM181mil to STP for refurbishment works to repair five sets of four-car monorail trains that have stopped working since January 2018.
Of the five sets of four-car trains, the first three trains will be repaired within three months of the start date of restoration work, while the remaining two trains will be refurbished within six months of the commencement date.
In a filing with Bursa Malaysia yesterday, it was said that payments of RM181mil by Prasarana would be utilised to make payments to STP’s lenders, creditors and employees.
Both parties will enter into a further agreement for the completion and delivery of seven, four-car monorail trains within 30 days of the condition precedents being met, or any other later date that is mutually agreed upon in writing at an expected cost of RM122mil.
According to news reports, the seven sets of new trains would be built in STP’s factory.
Yesterday, the agreement was signed by Scomi Group CEO Sammy Tse Kwok Fai and Prasarana president and CEO Datuk Mohamed Hazlan Mohamed Hussain. The signing was witnessed by Transport Minister Anthony Loke.
Although the new agreement will settle legal disputes between both parties, Loke said it would also mitigate the falling ridership, which has fallen 54.9% to 32,000 passengers per day currently from 71,000 passengers per day in 2015 mainly due to fewer operational trains.
Going forward, Scomi said the settlement is expected to contribute positively to the future earnings and earnings per share of the company, given that both STP and Prasarana fulfil the terms and conditions of both refurbishments and the purchase of the new train sets.
“The board is of the opinion that the settlement is in the best interest of the company and its subsidiaries,” the group said.
This book is the result of the author's many years of experience and observation throughout his 26 years in the stockbroking industry. It was written for general public to learn to invest based on facts and not on fantasies or hearsay....
solid
401 posts
Posted by solid > 2019-03-26 16:25 | Report Abuse
https://www.theedgemarkets.com/article/scomi-energy-bags-contracts-worth-rm610m-kuwait