The turnaround to Profitability was mainly from the share of profit in the Vietnam joint venture which amounted to RM 140.7 million in FYE2021 as compared to RM3.8 million in the previous year .
B ) Referred to FY22 Annual Report :
The increase in Profitability arose from the Higher share of Profit from the Vietnam joint venture that rose by 11 % to RM 156.2 million.
C ) Referred to 1st QR ended March 2023 :
Share of Profit in Joint Venture is RM 28,326,000 compared to March 2022 RM 33,936,000.
—
>> JHDP has been granted the Investment Certificate by the Ministry of Planning and Investment of Vietnam on June 2011 to develop a 2 x 600 MW Coal Fired Thermal Power Plant Project in Phuc Thanh Commune, Kinh Mon District, Hai Duong Province, Vietnam ("Hai Duong BOT Thermal Power Plant"), under the form of Build-Operate-Transfer ("BOT") for 25 years.
>>> Construction of Hai Duong BOT Thermal Power Plant has commenced in the first half of 2016. Hai Duong BOT Thermal Power Plant achieved the commercial operation for its first unit on November 2020, while the commercial operation for the second unit was achieved in January 2021.
This book is the result of the author's many years of experience and observation throughout his 26 years in the stockbroking industry. It was written for general public to learn to invest based on facts and not on fantasies or hearsay....
Johnchew5
11,612 posts
Posted by Johnchew5 > 2023-07-27 15:08 |
Post removed.Why?