Indian movie soon or later need to close. The buffalo don't have sufficient cash flow to continue subsidize the daily operation cost for both unit of 5 million per month. Now unit 2 failed to supply to main grid.
That cbai telling ppl how good with supply calculation and asked ppl to hold for 3 years. After making big gain and run, now talk bad about the management and plant.
Don't worry the monkeys will decide to off load the 20 % off Indian plant cos bankers will come after their debts especially sukuk of 1 billion and Ipp loan.
SO LOOKS LIKE INDIAN PROJECT IS NOT GOING TO BRING ANY PROFIT INCOME AT THE MOMENT, WITH SO MANY UNSETTLE ISSUES, WITH DEBTS RUNNING HIGH...IF THIS NOT SETTLE SOON, THE WHOLE LUMP OF SHIT WILL BE HANDED OVER TO A NEW MANAGEMENT... NOW THIS WILL BE THE BALANCE GAMES LEFT, TO CHANGE MANAGEMENT ALWAYS, PASS THE SHIT FROM HAND TO HAND...I AM VERY VERY SURE THEIR PLACEMENT EXERCISE WILL ALSO BE A FAILURE
Not much of the instituitional investors will be interested with their placement exercise, because not covered my any research houses..now all reseach houses has stop covering up this counter, because always talking lies and playing Delay tektics...this company is a VERY TIGHT ZIP MOUTH COMPANY, won t share any truth with research houses, but they only will share it with their inner choosen CLANS..
ha ha ha no discount anymore for placements....that day very proudly the puki company was saying discount from the price of 1.38.. now what happen to 1.38...they can shaft it in their asses
Anything coming, only the inner choosen CLANS MEMBERS will know first, they usually will buy in, then after few days then a devil like RHB WILL BLOW THE TRUMPHET, and will announce the reason why the counter is going up..by then it will be too late for retail investors to buy in cause the counter already reach to it s support levels...but some still will be buying but the CLANS DEVILS WILL BE SELLING...WHY THE F...KING EYES OF SECURITY COMMISSION ARE BLIND, OR MAYBE THEY ARE ALSO INVOLVE IN THIS GAMES
Heaven to do business in india is not a joke, all are croooks there, just waiting to eat you right to your bones, if they can catch your soul, they will do it also, swallow it completely in their throats..this mudajaya is a straight forward company, but now already went to india, join them for many years, now became crooks like them
By Adam Aziz | 2017-07-31 20:49:43 KUALA LUMPUR (July 31): Mudajaya Group Bhd has bagged two contracts worth RM151.38 million from Petroliam Nasional Bhd (Petronas) to undertake procurement, construction and commissioning (PCC) works for the utilities, interconnecting and offsite (UIO) facilities of the refinery and petrochemical integrated development (Rapid) project in Pengerang, Johor.
In a filing with Bursa Malaysia today, Mudajaya said its wholly-owned unit Mudajaya Corp Bhd was awarded the two contracts on July 25 and 26 by PRPC Utilities and Facilities Sdn Bhd, a subsidiary of Petronas.
Project 1 involves PCC of a data centre and telecom equipment room and an electrical substation for the UIO facilities at the Rapid project, while Project 2 involves PCC of civil and infrastructure works at Area 8100 for the UIO facilities.
"Project 1 is targeted to be fully completed by July 2018 with a construction period of 12 months from the date of the letter of award, while Project 2 is targeted to be fully completed by March 2018 with a construction period of eight months from the date of the letter of award," said Mudajaya.
The projects are expected to contribute positively to the earnings of the group for the financial year ending 2017 and onwards, it added.
Mudajaya shares closed 3 sen or 2.34% lower at RM1.25 today, for a market capitalisation of RM673 million.
This book is the result of the author's many years of experience and observation throughout his 26 years in the stockbroking industry. It was written for general public to learn to invest based on facts and not on fantasies or hearsay....
heaven123
1,900 posts
Posted by heaven123 > 2017-07-23 13:36 | Report Abuse
Indian movie soon or later need to close.
The buffalo don't have sufficient cash flow to continue subsidize the daily operation cost for both unit of 5 million per month.
Now unit 2 failed to supply to main grid.