Cmy119..the news is about preQ to be issued for FEED (Front End Engineering Design)..it will take about 6-12 months for the FEED engineering duration; follow-up with Detailed Design Engineering (whether by client or contractor) for another 12-16 months (or more) for Platform weight 26,000MT; construction at least 24 months; after that baru lah offshore activities...
so approximately 3.5-4+ years before Alam can participate..itu pun kena bid dulu baru boleh dpt project